Today we will continue the works started last week. Carrying out alterations to property downpipes, inserting bends onto the down-pipes to direct water across the footways, through fluted channels.
This week we will be working through a remedial list which consists of a variety of defects mainly damage to rendering and wooden fascia panels. All rendering defects are completed apart from the painting of them which is in hand. A local carpenter is repairing damage to wooden fascia panels.
Resurfacing Works
Due to the adverse weather this weekend the plane out and laying of binder course from the start of High Street to Back Fields at the bottom end of Old Street was cancelled. A new program of works will be issued in this circumstance. This week we will be working through a remedial list which consists of a variety of defects mainly damage to rendering and wooden fascia panels. All rendering defects are completed apart from the painting of them which is in hand. A local carpenter is repairing damage to wooden fascia panels.
Resurfacing Works
The picture above shows some of the completed footway resurfacing earlier on this month.
Please note that our Liaison Officer Terry Godwin is on Holiday next week from Monday 25th March, 2013 to Monday 1st April, 2013 so if you would like further information please visit this blog site which is updated daily.
Alternatively please telephone our Customer Care Line on 01905 761176.