Monday, 18 March 2013

Upton-upon-Severn - High Street & Old Street improvement works

Today we will continue working on the High Street and Church Street area installing drainage channels.

The work carried out this Sunday went well and to plan. See below pictures showing the planned surface and the carriagway surface with the base course laid.


A road closure will be necessary next Sunday 24th March on the High Street, Lower High Street, Old Street and Church Street area to enable us to lay the top course to the carriageway.
We appreciate you patience and understanding whilst we carryout these works.
The blog is updated daily so please visit regularly for up to date information. 
Alternatively you can speak to our Liaison Officer Terry Godwin, who will be regularly available "on site" or at our site office at 38 Old Street during the works to listen to any concerns or issues.