This week we have been carrying out alterations to property downpipes, inserting bends onto the down-pipes to direct water across the footways, through fluted channels.
We have a remedial list which consists of a variety of defects mainly damage to rendering and wooden fascia panels. All rendering defects are completed apart from the painting of them which is in hand. Photographic evidence of damage to wooden fascia panels will be handed to a local carpenter today with a view to completing the works next week.
We have arranged for a window cleaner to clean all windows on shop frontages and private property where reconstruction works have taken place, this will not be done until all resurfacing works are completed (15th April, 2013).
Resurfacing Works
The resurfacing work has to be done under a road closure due to the nature of the work and the width of the roads. The work is being carried out on Sundays only and the road will be open at all other times. The work is weather dependent, the current programme is:-
Sunday 17/03/2013 Closure of High Street plane out the carriageway and laying binder course - Completed
Sunday 24/03/2013 Closure of Old Street to plane out and lay binder course from the start of High Street to Back Fields at the bottom end of Old Street.
Sunday 31/03/2013 No work due to Bank Holiday
Sunday 07/04/13 Closure of High Street and Old Street to lay wearing course and replace the lining in Old Street,the Bus Stop and disabled parking in High Street.
Sunday 14/04/2013 Closure of High Street to complete the surfacing work and lining on adjacent road junctions to High Street.
Please note that our Liaison Officer Terry Godwin is on Holiday next week from Monday 25th March, 2013 to Monday 1st April, 2013 so if you would like further information please visit this blog site which is updated daily.
Alternatively please telephone our Customer Care Line on 01905 761176.