Wednesday, 3 April 2013

Upton-upon-Severn - High Street & Old Street improvement works

A local carpenter will be repairing damage to wooden fascia panels week commencing 8th April, 2013. This will complete the remedial list with just the resurfacing of the road to complete the improvement works.

The resurfacing work that has to be done will be carried out under a road closure, due to the nature of the work and the width of the roads. The work is being carried out on Sundays only and the road will be open at all other times. The work is weather dependent, the current programme is :-

Sunday 07/04/2013 closure of High Street to plane out and lay binder course from the start of the High Street to Back Fields at the bottom end of Old Street.
Sunday 14/04/2013 closure of High Street and Old Street to lay wearing course and replace the lining in Old Street and the Bus Stop and disabled parking in High Street.
Sunday 21/04/2013 closure of High Street to complete the surfacing work and lining on adjacent road junctions to High Street.

Advance yellow warning board signs have been put up to advise of the closure.

We will endeavour to keep disruption to a minimum during this period and we would very much appreciate your patience and cooperation during the completion of these works.

We will be updating this blog on a daily basis (Monday to Friday) so please ensure you visit regularly for updates on the progression of this scheme.  Information on our other road works throughout the County of Worcestershire can be found on our Twitter feed www.twitter.com/roadworks_info