Today we will continue laying the new kerbing on Lower High Street.
On Monday we will be working on the east side of the High Street (White Lion Hotel side) excavating the kerbline and relaying new kerbs.
All this work can be done without the use of traffic signals or road closures and should not impede the traffic flow, due to the width of the High Street.
The road closure booked for Old Street for 4th February, 2013 has been put back a week to 11th February, 2013 due to the current flooding.
We will be monitoring river levels next week and will continue to update this blog on a daily basis to provide the most up to date information.