Thursday, 28 February 2013

Upton-upon-Severn - High Street & Old Street improvement works

Today we will be working on the High Street outside the White Lion Hotel and Backfields Lane junction with Old Street constructing a build out of the pavement.

Traffic management will not be required to carryout this work.

Tomorrow we will be working in the High Street laying the red ashphalt surface course to the footway.
We have been advised that Old Street will be closed this Sunday 3rd March, 2013 but this is for works by another contractor and does not relate to our improvement works.

We appreciate your patience and understanding whilst we carryout these works.
This blog is updated regularly so please visit daily for up to date information.

Wednesday, 27 February 2013

Upton-upon-Severn - High Street & Old Street improvement works

Today we will be working on the High Street, west side laying the red ashphalt surface to the footway. Drainage and kerbing works will also be taking place on Old Street.

To ease traffic movement today Stop and Go will be used instead of traffic lights at the junction with Church Street and High Street.

We appreciate your patience and understanding whilst we carryout these works.
 
The blog is updated regularly so please visit daily for up to date information.

Tuesday, 26 February 2013

Upton-upon-Severn - High Street & Old Street improvement works

Today we will be working in Church Street excavating and laying the basecourse to the footway.

To ease traffic movement today we will use Stop and Go instead of traffic lights.

We appreciate your patience and understanding whilst we carryout these works.
 
The blog is updated regularly so please visit daily for up to date information.

Monday, 25 February 2013

Upton-upon-Severn - High Street & Old Street improvement works

Today we are continuing to work on the west side of the High Street into New Street  renewing the kerbs.

Tomorrow we will be working in Church Street excavating and laying the basecourse to the footway.

To ease traffic movement tomorow we will use Stop and Go instead of traffic lights.

We appreciate your patience and understanding whilst we carryout these works.

Thursday, 21 February 2013

Upton-upon-Severn - High Street & Old Street improvement works

Today we are working on the west side of the High Street renewing kerbs and excavating the footway.
 
Tomorrow we will be working on the west side of the High Street again excavating the footway and laying the basecourse.

Works will take place on Old Street this Sunday 24th February, within a road closure. This will consist of excavating the existing surface and laying of the basecourse to tarmac.

We appreciate your patience and understanding whilst we carryout these works.

Wednesday, 20 February 2013

Upton-upon-Severn - High Street & Old Street improvement works

Today surfacing works took place on Old Street, the works on Court Street have proceeded ahead of schedule therefore the road closure is being removed to minimise any possible disruption.

The works planned for 21st February will consist of renewing kerbs and excavating the footway on High Street.



Works will take place on Old Street this Sunday 24th February, within a road closure. This will consist of excavating the existing surface and laying of the basecourse to tarmac.

We appreciate your patience and understanding whilst we carryout these works.

Monday, 18 February 2013

Upton-upon-Severn - High Street & Old Street improvement works

Today we will be installing kerbing and concrete drainage channels in Old Street. If this goes to plan this afternoon we will start laying the red ashphalt surface course along New Street.

Court street will be closed today for some drainage works to take place.  As a result of this and to minimise any potential further disruption some patchway works will also be carried out at the same time.  

We will continue to update this blog on a daily basis to provide the most up to date information.

Friday, 15 February 2013

Upton-upon-Severn - High Street & Old Street improvement works

Today we are continuing to lay the red ashphalt surface course along Church Street and at the junction with High Street (East Side) into New Street.



On Monday and Tuesday next week we will be working in Old Street installing the kerbing and fluted channels to the footpath. We will also start excavating and laying binder course on the High Street west side.

As previously advised Old Street will no longer be closed on Sunday 16th February, 2013.  As a result of this and to minimise any potential disruption the works are being rescheduled . We will advise dates as soon as possible.


We will continue to update this blog on a daily basis to provide the most up to date information.

Thursday, 14 February 2013

Upton-upon-Severn - High Street & Old Street improvement works

Today the works are going as previously advised the attached photo shows the red ashphalt being laid



Tomorrow we plan to continue working on the east side of the High Street where we will be laying the surface course to the footway and excavating the kerbline.

We will be monitoring river levels this week and will continue to update this blog on a daily basis to provide the most up to date information

Wednesday, 13 February 2013

Upton-upon-Severn - High Street & Old Street improvement works

Today we will continue excavating the footway on New Street to the end of the shops. New kerb stones will also be laid.



This work can be carried out without the use of traffic signals or road closures and should not impede on the traffic flow.

Thursday and Friday this week we plan to work on the High Street where we will be laying the wearing course to the footway and excavating the kerbline.

We will be monitoring river levels this week and will continue to update this blog on a daily basis to provide the most up to date information.

Tuesday, 12 February 2013

Upton-upon-Severn - High Street & Old Street improvement works

Today and tomorrow we will be excavating the footway on New Street to the end of the shops. We will also be laying new kerb stones.

This work can be carried out without the use of traffic signals or road closures and should not impede on the traffic flow.

Thursday and Friday this week we plan to work on the High Street where we will be laying the wearing course to the footway and excavating the kerbline.

We will be monitoring river levels this week and will continue to update this blog on a daily basis to provide the most up to date information.

Monday, 11 February 2013

Upton-upon-Severn - High Street & Old Street improvement works

Due to the current cold weather conditions, improvements works have been affected.  The work that was scheduled for Old Street yesterday and today has been postponed.
 
A new programme of works will therefore need to be put in place.

We will continue to update this blog on a daily basis and will provide information as soon as we can, notifying as to when the works will re-commence once the cold weather has started to clear.

We apologise for any inconvenience circumstances beyond our control may have caused.

Friday, 8 February 2013

Upton-upon-Severn - High Street & Old Street improvement works

Today we are returning to Old Street (west side) to continue excavation of the footway ready for the binder course to be laid. There will also be some kerb repairs.


This work will be carried out using two way temporary traffic lights.

Old Street will no longer be closed from Monday 11th to Friday 15th February. As a result of this and to minimise any potential disruption the works have been rescheduled to be carried out over the next three consecutive Sundays. These days being Sunday 10th,17th and 24th February and will be carried out under road closures.

We will continue to update this blog on a daily basis, so please visit for the latest information on progress.

Thursday, 7 February 2013

Upton-upon-Severn - High Street & Old Street improvement works

Today we are returning to Old Street (west side) to continue footway and kerbing works.

This work will be carried out using two way temporary traffic lights.

Old Street will no longer be closed from Monday 11th to Friday 15th February. As a result of this and to minimise any potential disruption the works have been rescheduled to be carried out over the next three consecutive Sundays. These days being Sunday 10th,17th and 24th February and will be carried out under road closures.

We will continue to update this blog on a daily basis, so please visit for the latest information on progress.

Wednesday, 6 February 2013

Upton-upon-Severn - High Street & Old Street improvement works

The works being carried out today are located at High Street (east side by the White Lion Hotel), these consist of footway construction and kerbing works.

On Thursday and Friday of this week, we will be returning to Old Street (west side) to continue footway and kerbing works, this work will be carried out under two way temporary traffic lights.

Old Street will no longer be closed from Monday 11th to Friday 15th February. As a result of this and to minimise any potential disruption the works have been rescheduled to be carried out over the next three consecutive Sundays. These days being Sunday 10th,17th and 24th February and will be carried out under road closures.

We will continue to update this blog on a daily basis, so please visit for the latest information on progress.

Tuesday, 5 February 2013

Upton-upon-Severn - High Street & Old Street improvement works

We will continue working on the east side of the High Street (White Lion Hotel side) excavating the kerbline and relaying new kerbs.


All this work can be done without the use of traffic signals or road closures and should not impede the traffic flow, due to the width of the High Street.

The road closure booked for Old Street for 4th February, 2013 has been put back a week to 11th February, 2013 due to the current flooding.

We will continue to update this blog on a daily basis to provide the most up to date information.

Monday, 4 February 2013

Upton-upon-Severn - High Street & Old Street improvement works

Today we will be working on the east side of the High Street (White Lion Hotel side) excavating the kerbline and relaying new kerbs.


All this work can be done without the use of traffic signals or road closures and should not impede the traffic flow, due to the width of the High Street.

The road closure booked for Old Street for 4th February, 2013 has been put back a week to 11th February, 2013 due to the current flooding.

We will be monitoring river levels this week and will continue to update this blog on a daily basis to provide the most up to date information.

Friday, 1 February 2013

Upton-upon-Severn - High Street & Old Street improvement works

Today we will continue laying the new kerbing on Lower High Street.

On Monday we will be working on the east side of the High Street (White Lion Hotel side) excavating the kerbline and relaying new kerbs.

All this work can be done without the use of traffic signals or road closures and should not impede the traffic flow, due to the width of the High Street.

The road closure booked for Old Street for 4th February, 2013 has been put back a week to 11th February, 2013 due to the current flooding.

We will be monitoring river levels next week and will continue to update this blog on a daily basis to provide the most up to date information.