Wednesday, 26 June 2013

Upton-upon-Severn - High Street and Old Street improvement works

The window cleaning has comenced today and will halt when the town livens up. It will re-continue tomorrow.

Wednesday, 24 April 2013

Upton-upon-Severn - High Street and Old Street improvement works

The carriageway surface course was laid on Old Street on Sunday 21st April, 2013 with road markings put in place.

This week the local carpenter is continuing repairs on various shop front facia's etc.

We expect this work to take the rest of this week.  There are also outstanding remedial works to be undertaken shortly.


Above are some pictures of the surfacing work carried out at the weekend.
 
We will endeavour to keep disruption to a minimum when these works are carried out and we would very much appreciate your patience and co-operation during this period..

We will be updating this blog on a regular basis so please ensure you visit for further information. Alternatively you can find updates regarding works in the area on our Twitter account www.twitter.com/roadworks_info

Tuesday, 23 April 2013

Upton-upon-Severn - High Street and Old Street improvement works

The carriageway surface course was laid on Old Street on Sunday 21st April, 2013 with road markings put in place.
This week the local carpenter is continuing repairs on various shop front facia's etc.

We expect this work to take the rest of this week.  There are also outstanding remedial works to be undertaken shortly.

Below are some pictures of the surfacing work carried out at the weekend.




We will endeavour to keep disruption to a minimum when these works are carried out and we would very much appreciate your patience and co-operation during this period..

We will be updating this blog on a regular basis so please ensure you visit for further information. Alternatively you can find updates regarding works in the area on our Twitter account www.twitter.com/roadworks_info

Wednesday, 17 April 2013

Upton-upon-Severn - High Street and Old Street improvement works

We are not planning any works to be carried out by ourselves until Sunday 21st April, these works will consist of laying the carriageway surface course on Old Street plus the undertaking of roadmarking works.



We will endeavour to keep disruption to a minimum when these works are carried out and we would very much appreciate your patience and co-operation during this period..
Later today the local carpenter should commence work on various shop front facia's etc.

We will be updating this blog on a regular basis so please ensure you visit for further information. Alternatively you can find updates regarding works in the area on our Twitter account www.twitter.com/roadworks_info

Tuesday, 16 April 2013

Upton-upon-Severn - High Street and Old Street improvement works

No works are planned to be carried out by ourselves until Sunday 21st April, these works will consist of laying the carriageway surface course on Old Street plus the undertaking of roadmarking works.

We will endeavour to keep disruption to a minimum when these works are carried out and we would very much appreciate your patience and co-operation during this period..

We will be updating this blog on a regular basis so please ensure you visit for further information. Alternatively you can find updates regarding works in the area on our Twitter account www.twitter.com/roadworks_info

Monday, 15 April 2013

Upton-upon-Severn - High Street and Old Street improvement works

Yesterday, the carriageway surface course was laid on Lower High Street and High Street in Upton; sections of the roadmarking was also relaid. On Sunday 21st April, the carriageway surface course will be laid on Old Street plus roadmarking will be undertaken.


We will endeavour to keep disruption to a minimum during this period and we would very much appreciate your patience and co-operation during the completion of these works.

We will be updating this blog on a regular basis so please ensure you visit for further information. Alternatively you can find updates regarding works in the area on our Twitter account www.twitter.com/roadworks_info.

Friday, 12 April 2013

Upton-upon-Severn - High Street and Old Street improvement works

The resurfacing that is due to take place this Sunday 14th April, 2013 will be carried out under a road closure. We will close the High Street and Old Street to lay the wearing course to the road surface and replace the lining in Old Street , the Bus Stop and disabled parking in High Street.

To avoid congestion in "Minge Lane" two "no through" road signs will be put in place. The local carpenter will also start work repairing the damage to wooden fascia panels.

We will endeavour to keep disruption to a minimum during this period and we would very much appreciate your patience and co-operation during the completion of these works.

We will be updating this blog on a daily basis (Monday to Friday) so please ensure you visit. Alternatively you can find updates regarding works in the area on our Twitter account www.twitter.com/roadworks_info.

See below pictures taken during the improvement works.